1260 S. Washington Street - Phone (419) 238-1417
City water was originally produced from a well that was located next to Jubilee Park. At the time, treatment included adding lime soda to soften the water. A reservoir of fifty-eight surface acres was built in 1949. It was designed to hold 380 MG (million gallons) of water. The treatment plant was built next to the reservoir and went into water production in 1951. A second reservoir,
built in 1964, was originally sixty-one surface acres and held 400 MG of water. Two domes were added to the north side of the treatment plant in 1979, along with other improvements that more than doubled the settling and clarification capabilities of the plant. The current plant is designed to treat 4.5 MG daily. In 1993-1995 CO2 induction, and filtration improvements were made.
|
|
|